Strategi Antisipasi Defect List Pada Pekerjaan Rigid Pavement Proyek Jalan Tol Trans Sumatera: Studi Kasus Ruas Pekanbaru-Padang = Anticipation Strategies for Defect List in Rigid Pavement Works of the Trans Sumatera Toll Road Project: Case Study of the Pekanbaru-Padang Section

Rohmat Romdhani; Jaka Fajar Fatriansyah, supervisor; Widjojo Adi Prakoso, examiner (Fakultas Teknik Universitas Indonesia, 2024)

 Abstrak

Pekerjaan rigid pavement pada proyek jalan tol Trans Sumatera ruas Pekanbaru-Padang merupakan salah satu tahap konstruksi yang sangat krusial dalam menjamin kualitas dan keberlanjutan jalan tol. Daftar ketidaksesuaian yang tercatat dalam Berita Acara (BA) PHO akibat berbagai faktor, seperti aspek teknis, keterbatasan sumber daya, hingga pengelolaan proyek yang kurang optimal. Penelitian ini bertujuan untuk mengidentifikasi jenis-jenis Defect List yang sering terjadi pada perkerasan rigid pavement, merumuskan langkah-langkah efektif untuk meminimalkan terjadinya Defect List, serta menganalisis risiko yang muncul akibat deffect rigid. Hasil penelitian menunjukkan bahwa penerapan strategi antisipasi mampu mengurangi jumlah Defect List. Pada lokasi yang penulis lakukan yaitu STA 58+400 hingga STA 60+200, jumlah Defect List yang ditemukan terdiri atas 9 defect minor dan 9 defect mayor. Angka ini lebih rendah dibandingkan dengan dua lokasi lainnya, yakni STA 55+200 hingga STA 57+000 dengan 15 defect minor dan 20 defect mayor, serta STA 60+200 hingga STA 62+000 yang mencatat 12 defect minor dan 32 defect mayor. Perbedaan ini diduga disebabkan oleh kurangnya penerapan langkah-langkah preventif pada lokasi-lokasi tertentu. Melalui penelitian ini, diharapkan menjadi panduan dalam pelaksanaan pekerjaan rigid pavement, sehingga kualitas konstruksi jalan rigid pavement dapat ditingkatkan dan diharapkan berkontribusi dalam pengembangan konstruksi jalan di masa mendatang.

The rigid pavement work on the Trans Sumatera toll road project section, Pekanbaru-Padang, is one of the most crucial construction stages in ensuring the quality and sustainability of the toll road.  The list of discrepancies recorded in the PHO Minutes of Meeting (MoM) is due to various factors, such as technical aspects, resource limitations, and suboptimal project management. This research aims to identify the types of Defect Lists that frequently occur in rigid pavement, formulate effective steps to minimize the occurrence of Defect Lists, and analyze the risks that arise due to rigid defects. The research results show that the implementation of anticipation strategies can reduce the number of Defect Lists. At the location I examined, namely STA 58+400 to STA 60+200, the number of defects found consisted of 9 minor defects and 9 major defects. This figure is lower compared to the other two locations, namely STA 55+200 to STA 57+000, which had 15 minor defects and 20 major defects, and STA 60+200 to STA 62+000, which recorded 12 minor defects and 32 major defects. We suspect that the lack of implementation of preventive measures at certain locations is the cause of this difference. This research aims to guide the implementation of rigid pavement work, enhancing its quality and potentially contributing to the future development of road construction.

 File Digital: 1

Shelf
 PR-Rohmat Romdhani.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Tugas Akhir
No. Panggil : PR-pdf
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Program Studi :
Subjek :
Penerbitan : Depok: Fakultas Teknik Universitas Indonesia, 2024
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : computer
Tipe Carrier : online resource
Deskripsi Fisik : xiv, 49 pages : illustration + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
PR-pdf 16-25-31298603 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 9999920564401
Cover